Precise calculations, great for complex scheduling of projects
Beoordeeld op 6-2-2019
I have been using Primavera for about 12 years now, and I've been training people how to use it,...
I have been using Primavera for about 12 years now, and I've been training people how to use it, I've managed to train government engineers, construction contractors, engineering firms, and sponsors, it has been a great experience, the program is very precise when it comes to time, cost, resource, risk, and schedule calculations (CPM, PERT).
Pluspunten
- Great for large scale projects
- Detailed scheduling with time and cost breakdown
- Perfect filtering features
- High level resource management functionality
- Expense distribution over activity duration
Minpunten
- Graphics are not very appealing
- Jumping between tabs on the lower ribbons is very annoying compared to the tabs functionality available now on office software, and Autodesk products

- Sector: Online media
- Bedrijfsgrootte: Zelfstandig ondernemer
- Dagelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 10.0 /10
Application built according to PMI Standards.
Beoordeeld op 24-6-2022
Pluspunten
The application structure is built according to PMI Standards and follows the processes exactly as described in PMBOK.
Minpunten
Time expent to configuration and implementation is high.

- Sector: Bouw
- Bedrijfsgrootte: 2-10 werknemers
- Maandelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 7.0 /10
Primavera has a need to make the software more user friendly
Beoordeeld op 15-6-2017
this software does what it is designed to do, just not in the easiest format to learn!
this software does what it is designed to do, just not in the easiest format to learn!
Pluspunten
I have used P3 and P6 now for years and find the software very powerful and thorough. I find that once you learn how to use the software it enables the company to be more efficient and productive.
Minpunten
The con to this software is the upfront cost, lack of training, and how complex the software is. They really need to improve their training! I will spend countless hours trying to get a newby up to speed on this software.

- Sector: Olie en energie
- Bedrijfsgrootte: 10.000+ werknemers
- Wekelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 10.0 /10
Primavera Cloud is a Cost saver.
Beoordeeld op 4-10-2022
Pluspunten
Primavera Cloud is really a good cloud-based application, earlier I used to have a system installed-based application but when the organization grows it becomes very difficult to buy more software on high cost .
But this cloud-based system solved that purpose.
Minpunten
I don't feel any such issue so far as I am using this from last 15 years.

- Sector: Bouw
- Bedrijfsgrootte: 1.001-5.000 werknemers
- Dagelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 10.0 /10
Project Planning Sheduling & Monitoring with Primavera
Beoordeeld op 17-1-2019
Very like, my overall profession "planning engineer" fully based on this software. Now i am using...
Very like, my overall profession "planning engineer" fully based on this software. Now i am using since 3 years this Oracle Primavera Project Management Software for getting the most success in every project till the handover.
Compatible with report generation.
Esay for analyzing reviewing of project progress status.
Can export to different files and easy sharing.
Updated versions coming more features continuesly.
Pluspunten
Complex, but it is full fix with more powerful tools which can help for more accurate project planning, scheduling and monitoring purposes.
Minpunten
Tools are little Complex - need more training and practice
Undo feature is not enabled

- Sector: Civiele techniek
- Bedrijfsgrootte: 201-500 werknemers
- Wekelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 8.0 /10
The Best Project Management Software for those who can afford it
Beoordeeld op 15-3-2021
Primavera is the class leading software when in comes to project management, if you can afford it....
Primavera is the class leading software when in comes to project management, if you can afford it. Although similarly featured, and relatively cheap Microsoft Project might be more popular, Primavera is your solution if you simply want the best. It's far more feature-packed, and if you are looking for the advanced tools for large and complex projects, it is better than MS Project in every way.
Pluspunten
Primavera offers the best in class project management tools for project planning, scheduling and almost everything you'd want when in comes to managing a project of any magnitude.
Minpunten
Unless your firm gives proper weightage to the soft tools required for proper planning and execution of projects, Primavera is going to come as a somewhat expensive option.

- Sector: Bouw
- Bedrijfsgrootte: 201-500 werknemers
- Wekelijks 6-12 maanden lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 10.0 /10
Feasibility Report of Oracle Primavera Cloud
Beoordeeld op 15-12-2022
Pluspunten
I like the interface of this software to use. Easy process to schedule the tasks associated with the activity and it can be easily integrated with MS Excel Software.
Minpunten
The complexity to allocating the resources while making a schedule on which is quiet easy on MS Excel.

- Sector: Entertainment
- Bedrijfsgrootte: 10.000+ werknemers
- Wekelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 9.0 /10
Primavera P6 is the scheduling standard
Beoordeeld op 19-12-2018
Pluspunten
The ability to build huge and complex schedules. P6 has been the construction scheduling standard for a while now. The ability handle the thousands of activities in a large project and adjust to the constant changes of the construction industry.
Minpunten
Primavera P6 is not an easy software package to learn and it is not very cheap. You get out what you put into the software and the skills it takes to learn it.

- Sector: Bouw
- Bedrijfsgrootte: 51-200 werknemers
- Dagelijks 1+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Gebruiksgemak
- Waarschijnlijkheid van aanbeveling 8.0 /10
Primavera
Beoordeeld op 30-8-2018
Pluspunten
Primavera works great for construction companies in tracking information from many areas
Minpunten
Primavera was limited in certain areas causing extra work.

- Sector: Managementconsulting
- Bedrijfsgrootte: 11-50 werknemers
- Maandelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 10.0 /10
Project Management, for Professionals
Beoordeeld op 12-4-2019
For Project Management software, I truly believe that despite its learning curve, Primavera is the...
For Project Management software, I truly believe that despite its learning curve, Primavera is the hands down winner. Comparatively to other project management software that is enterprise-wide (minus the free or cheap version for small teams), Primavera stands tall.
Pluspunten
I can't stress enough that the amount of features in Primavera makes scheduling, baselining, statusing for large and small scale projects so detailed. You can add copious amounts of details that can be relevant to both the PDT and the client.
Minpunten
Primavera is honestly fairly hard to learn and takes even longer to master. The longer you learn and live in the system, the better you get. Training is definitely not enough to learn how to master the system.
- Sector: Architectuur en planning
- Bedrijfsgrootte: Zelfstandig ondernemer
- Maandelijks 6-12 maanden lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 8.0 /10
Very functional
Beoordeeld op 5-8-2023
Good considering value for money and functionaility, the interface and design could be upgraded to...
Good considering value for money and functionaility, the interface and design could be upgraded to keep up with other similar softwares but it gets the job done in a timely manner.
Pluspunten
Very functional and gets project management fast and makes prioritizing easier and faster, also it's nice that you can visualize some timeline.
Minpunten
Not the most user friendly, when it comes to finding specific tools and options, takes time to get used to its system, it was not easy to navigate as a first timer without help from tutorials.
- Sector: Bouw
- Bedrijfsgrootte: 51-200 werknemers
- Dagelijks Gratis proef lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Waarschijnlijkheid van aanbeveling 8.0 /10
The Best Planing Management Software
Beoordeeld op 8-4-2023
although of the cost, Oracle Primavera Cloud is at the top of Project Management.
although of the cost, Oracle Primavera Cloud is at the top of Project Management.
Pluspunten
Most Planning Engineers have a good experience with this software. and the cloud version reduces the effort of installation and troubleshooting that's was a big effort.
Minpunten
The Price is very high, and when you need to upgrade to the cloud version the integration will be more hard than on-premise.
- Sector: Bouw
- Bedrijfsgrootte: 201-500 werknemers
- Dagelijks 6-12 maanden lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 8.0 /10
A must For Every Project Managers
Beoordeeld op 17-9-2017
I have used MS Project in my College days and we use to work on extracts of the Big Commercial and...
I have used MS Project in my College days and we use to work on extracts of the Big Commercial and Private Project and it explained us the little and major differences between the MS Project and Primavera. Primavera is overall the best detailed software for Project Management Professionals out there.
Pluspunten
The main thing WBS is seperated from the activties. You can add sub-activities and even the minor expenses like travelling and training costs. You can put in the percentage of completion in the sub-activities. Since it is EPPM software you can work on multiple projects. It's user defined controls and access makes it more easier to set roles and responsibilities to each and every OBS and activities and only allows multiple users to work at the set EPS & WBS level as per pemissions allowed.
I was once working on a Villa project and we had the option to set more than one relationship between two activities. You can also create resources as per composition based on the Schedule of Rates(SOR) from whichever region you are working from. It makes it more easier to assign for a particular project.
One another big benefit is that you can create 'n' number of Baselines as compared to other project management softwares. You can add risk and issues as well. Overall I feel Primavera P6 EPPM is a detailed project management software and you can work it at any verticals and horizontals.
Minpunten
What i don't like about this software is that it doesnt allow multiple entries on it's own based on the formulae set. Again you need to check out your project and schedule with correct date and time, well that is plus point definitely but in case you missed the proper date and time as per your working calender then it will affect the project at a minor level initially and major differences will be made if that remains ignored. Another drawback for it is that if you are working on a single project then it will require lot of detailing for WBS, OBS, EPS, Roles and responsibilities which can be unnecessary in some cases. You have to remember each and every detail wherever you are putting it.
- Sector: Design en ontwerp
- Bedrijfsgrootte: 10.000+ werknemers
- Dagelijks 6-12 maanden lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 10.0 /10
Primavera is a life saver
Beoordeeld op 3-12-2019
Overall I really love the software and the problems it solves. I am able to export to an excel file...
Overall I really love the software and the problems it solves. I am able to export to an excel file to analyze which makes things a lot easier for me. Then I can re-upload the excel file and it will adopt any changes I have made in the spreadsheet.
Pluspunten
I love how easy is it to see linked attributes in the gantt chart. There is simple connecting and coloring that allows you to track exactly where you are on a program, project or task level. It is relatively easy to use. As long as you are familiar with Excel you should be able to use most of the basic features. The WBS structure is similar to other programs I've worked in and the ability to copy and past at different levels helps to speed up the setup of a project.
Minpunten
There are a ton of functionality with the software but I have found it difficult to get any instruction or help when I get into some of the more complex features. Googling is about your best bet when you have a questions about something. There have also been some issue when you switch between versions. New versions aren't able to connect to the older version's server and therefore do not have access to the other schedules.
- Sector: Civiele techniek
- Bedrijfsgrootte: 51-200 werknemers
- Dagelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 8.0 /10
Oracle Primavera
Beoordeeld op 14-2-2019
I would say that it is less challenging to use primavera than Microsoft project.
I would say that it is less challenging to use primavera than Microsoft project.
Pluspunten
It is best project management software, planning, scheduling, resource managing, controlling can be done for any project . Eventhough it is a complex analysis and process, It is not much difficult to use.
Some advance features like top-down scheduling, longest path critical activity definition , activity steps and etc are now available . VBA is not required to separate and material cost.
Minpunten
In my experience, It would be slightly difficult to adopt for beginner.
- Sector: Bouw
- Bedrijfsgrootte: 11-50 werknemers
- Wekelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 10.0 /10
Primavera
Beoordeeld op 3-10-2021
Very Good so far
Very Good so far
Pluspunten
The professionalism of the software. the different aspects and tools .. the importance of arranging ideas and resources
Minpunten
it breaks sometimes i dont know why . the import and export of files is a difficulity
- Sector: Nutsbedrijven
- Bedrijfsgrootte: 10.000+ werknemers
- Dagelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 10.0 /10
Unique project management software
Beoordeeld op 26-9-2021
if you are searching for a great software for project management , don't hesitate using primavera ...
if you are searching for a great software for project management , don't hesitate using primavera
it's an effective software in term of time management ,task management and risk management
Pluspunten
effective and helpful
time management and risk management plans
it contain a samples for educational purposes
well organized software
helpful for all ages
Minpunten
it's a great software ,very helpful and reliable
suitable for students and project engineers and of course managers
suitble for creating primary and final plan for any project even if it's small or big project or just study plan
- Sector: Bouw
- Bedrijfsgrootte: 1.001-5.000 werknemers
- Wekelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 10.0 /10
Dependable Planning and Scheduling
Beoordeeld op 19-9-2018
Very reliable and convenient to use specially the interfacing between Prism G2 and this software. ...
Very reliable and convenient to use specially the interfacing between Prism G2 and this software. In just one click of a button data are transferred instantly and assigned to the proper linked data in Prism. Schedule and progress between two software coincides with each other making it more better for Management to analyze schedule and cost result and can deliver good decisions to a project using this software.
Pluspunten
User friendly scheduling and Planning tool, new cloud based data make it more easier to access remotely.
Minpunten
None, all functions works well for us for the project and from the company.
- Sector: Bouw
- Bedrijfsgrootte: 1.001-5.000 werknemers
- Wekelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Gebruiksgemak
- Waarschijnlijkheid van aanbeveling 9.0 /10
Suitable for scheduling!
Beoordeeld op 15-2-2021
I have used this software on multiple projects and I can safely say that it is a very useful and...
I have used this software on multiple projects and I can safely say that it is a very useful and user friendly software.
Pluspunten
The software to easy to use. The option of tracking the actual project performance against is the baseline is one of the best features of this software.
Minpunten
Sometimes when you hit the execute button, it changes the dates which are not meant to be changed. It can be due to poor constraints defined by the user but it becomes a little irritating.
- Sector: Bouw
- Bedrijfsgrootte: 11-50 werknemers
- Dagelijks 1+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 7.0 /10
Primavera
Beoordeeld op 5-5-2022
Overall this is an awesome program to work with and it's super powerful for what we use it for and...
Overall this is an awesome program to work with and it's super powerful for what we use it for and there are more options features that we have not use. But it is there if we ever require to use it.
Pluspunten
Great program with featured packed for everything that is required to schedule. We did also linked it up to REVIT so the schedule and the 3D model can work together and show the build up.
Minpunten
A long learning curve but once you figure out the short cuts then this program is awesome.

- Sector: Civiele techniek
- Bedrijfsgrootte: 51-200 werknemers
- Wekelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 8.0 /10
Academic use
Beoordeeld op 12-10-2018
I have been satisfied overall
I have been satisfied overall
Pluspunten
- Easy to use
- Includes resources, cost, and risk
Minpunten
- Sometimes you would have to click on WBS and go back to Activities in order for it to allow you to add an activity (for add add activity not to be ghosted). Could be a glitch.
- sometimes when adding WBS list, it does not show it in order you have listed it on the Activities
- Sector: Nutsbedrijven
- Bedrijfsgrootte: 5.001-10.000 werknemers
- Anders 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 10.0 /10
Highly recommended scheduling software
Beoordeeld op 20-10-2019
Software does very well in managing the mega project we are working with.
Software does very well in managing the mega project we are working with.
Pluspunten
This is the best tool available to manage project schedules of any size. This software is the industry standard when it comes to scheduling.
Minpunten
Nothing to dislike for this software. Schedules built using this can be shared and collaborated on. Allows easy data manipulation via Excel dumps.
- Sector: Bouw
- Bedrijfsgrootte: 201-500 werknemers
- Wekelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Prijs-kwaliteitverhouding
- Gebruiksgemak
- Klantenondersteuning
- Waarschijnlijkheid van aanbeveling 0.0 /10
It worked for what we needed
Beoordeeld op 25-1-2017
We used Primavera primarily for Project Management. Submittals, Pay Apps, Transmittals. For the...
We used Primavera primarily for Project Management. Submittals, Pay Apps, Transmittals. For the most part it was great. Especially once you got used to the system (It was not user friendly to all). The software was dependent on a particular version of IE and you could NEVER update your JAVA ever! Otherwise, it just wouldn't work. In the early years (before Oracle) the customer service was fantastic. However, since Oracle took over, the customer service has been terrible. We have since switched to a different software.
Pluspunten
It managed documents very well. Once used to the system and formats it was easy to use. Early on customer support was amazing.
Minpunten
Current customer support by Oracle is terrible. EI and Java could never be updated otherwise the software would not function.

- Sector: Bouw
- Bedrijfsgrootte: 501-1.000 werknemers
- Wekelijks 2+ jaar lang gebruikt
-
Bron van de reviewer
Totaalscore
- Gebruiksgemak
- Waarschijnlijkheid van aanbeveling 7.0 /10
Primavera Project Management
Beoordeeld op 9-1-2019
Overall, Oracle Primavera Project Management is a great tool to keep track of progress of all...
Overall, Oracle Primavera Project Management is a great tool to keep track of progress of all aspects in construction.
Pluspunten
Full of useful features for construction professionals. Maintain your budget and and track your progress.
Minpunten
A bit confusing at first. Training in the use is highly recommended.
- Sector: Bouw
- Bedrijfsgrootte: 11-50 werknemers
- Wekelijks 6-12 maanden lang gebruikt
-
Bron van de reviewer
Totaalscore
- Gebruiksgemak
- Waarschijnlijkheid van aanbeveling 10.0 /10
Great tool for developing detailed schedules
Beoordeeld op 10-12-2018
My experience with Primavera was using Primavera 6 (P6) with a construction management consulting...
My experience with Primavera was using Primavera 6 (P6) with a construction management consulting firm. The firm used it to create detailed schedules for various types of construction projects.
Pluspunten
Primavera allows you to go into as much detail as you want. The schedules created in the program can be an overview or down to the details of resource allocation. This makes the program versatile and usable in any situation the user needs.
Minpunten
There is a slight learning curve that may prove frustrating to some. I would recommend purchasing a exercise book or another resource to learn how to use the program.